Project Blue remains a high-priority Tucson/Pima County record because Tucson rejected the annexation and development agreement, but the county-side project continued through land, water-well, and electric-service pathways. NDA, land-sale, water, power, and public-cost records should stay visible for review.
ProposedconfirmedHigh concern
Site Snapshot
Location
Pima County / Tucson, Arizona
Operator / sponsor
Amazon Web Services / Beale Infrastructure
Status / stage
Proposed · approval / land-use
Scale
290-acre campus proposal
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
Public land-sale and economic-development negotiations were central to the local dispute; project-specific incentive, utility-cost, and public-benefit records still need review.
Source reviewed September 14, 2026: AZPM reported that Arizona water officials approved two commercial wells tied to Project Blue under three existing groundwater rights totaling 96.5 acre-feet per year. The Arizona Department of Water Resources told AZPM that annual water-use reporting is required; the article says each well was described as having 600 gallons-per-minute pumping capacity. This establishes a permitted supply path, not measured use, wastewater discharge, or proof of the developer's estimated 15,000–20,000 gallons per day once fully operational. The County's projected reclaimed-water allocations and water-capacity letters remain planned terms; final withdrawal, cooling, wastewater, and operating-use quantities remain unresolved.
Source reviewed September 13, 2026: the Arizona Corporation Commission says it approved TEP's special electric-service agreement for Project Blue and describes an initial anticipated load of 286 MW, with additional generation beyond that amount to be paid by the data center. TEP's agreement summary says the deal also includes minimum monthly bills, financial security, and a termination fee if the project does not meet its obligations. TEP's June 2026 Form 10-Q says FERC approval triggered a $20 million customer advance for transmission and switchyard construction, with another $24 million expected after remaining conditions. These are approved planned utility terms and reported customer advances, not proof of energized capacity, actual operating bills, or data-center IT load; the project's full campus scale remains unclassified.
Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.