Proposed-site record

Mountaineer Gigasystem/ Monarch Cloud Campus

Crowdsourced lead with high location confidence. Use the linked sources to verify status, public money, NDA/secrecy, water, and power details before treating this as a fully documented local record.

ProposedconfirmedMedium concern

Site Snapshot

Location
Point Pleasant, Mason County, West Virginia
Operator / sponsor
Nscale (acquired American Intelligence & Power; site formerly associated with Fidelis)
Status / stage
Proposed · approval / land-use
Scale
2000-8000 MW reported; Mega campus (>1,000 MW); 2250 acres; expected online 2028
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area · Target online date

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Nscale's current Monarch page reports more than $20 billion in planned capital investment and $80 million-plus in annual West Virginia tax revenue, including a projected $40 million for Mason County schools. These are company-stated plans/projections, not completed spending, public subsidy, or verified receipts; the source dataset's $5 billion project-cost lead remains historical context.

Water

Nscale's current Monarch page describes closed-loop cooling and says no municipal drinking water is used for operations. This is a company operating-design claim; the reviewed public material does not establish a water withdrawal, discharge, permit quantity, or measured consumption.

Power

Nscale's March 16, 2026 release describes an onsite microgrid with 2 GW expected online in the first half of 2028 and expansion to approximately 8 GW planned for 2031. Its Monarch page separately describes 1.35 GW of Phase 1 AI computing capacity. These are company-stated planned generation/power and compute-capacity contexts, not energized capacity or an independently verified IT-load measurement; the dataset's 2,000-8,000 MW remains unclassified.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.