Hanover County and Tract records document a rezoned, planned technology park with approved enabling permits, a submitted 2,400 MW load request, and planned water/sewer connections. The 2,400 MW remains planned requested-load and campus context rather than confirmed energized or IT-load capacity.

ProposedconfirmedMedium concern

Site Snapshot

Location
Ashland, Hanover County, Virginia
Operator / sponsor
VALCO HANOVER COUNTY
Status / stage
Proposed · approval / land-use
Scale
2400 MW reported; Mega campus (>1,000 MW); 11,000,000 sq ft; 1212 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

No public funding record attached yet. Local subsidy, tax-abatement, land, bond, and utility records need follow-up.

Water

Source reviewed September 9, 2026: Hanover County's project FAQ says the campus would connect to county water and sewer, with water from Hill Carter Booster Pump Station and sewer routed to the Ashland Treatment Plant; it says the existing system had sufficient capacity for the forecasted demand and that the campus would require about 3% of current county water-supply capacity. These are planning statements, not a final withdrawal, consumption, cooling, or wastewater measurement.

Power

Source reviewed September 9, 2026: Tract's site page describes up to 2,400 MW across eight Dominion Energy substations, while Hanover County's project FAQ says 2,400 MW matches the submitted load request to Dominion. This is a developer/county-reported planned utility-load request and campus scale, not proof of approved, energized, generation, or data-center IT-load capacity.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecy, Public moneyFields with source leads: Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.