Proposed-site record

Province Group @Powhatan Technology Park

Powhatan County approved Province Group's 181-acre planned campus and identifies available water/sewer capacity; Dominion's reported 365 MW initial deployment and county's 300-400 MW full-buildout estimate remain planned service context. The dataset's 365-2,400 MW range, facility water use, wastewater quantity, energized capacity, IT load, and public subsidy remain unresolved.

ProposedconfirmedMedium concern

Site Snapshot

Location
MIDLOTHIAN, Powhatan County, Virginia
Operator / sponsor
Province Group
Status / stage
Proposed · approval / land-use
Scale
365-2,400 MW reported; Mega campus (>1,000 MW); 2,000,000 sq ft; 180 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Source reviewed September 9, 2026: Powhatan County estimates approximately $10 million in additional annual property-tax revenue from the planned campus and Province/JLL reports a $3 billion project. These are projected investment and tax-revenue context, not completed spending or a verified public subsidy.

Water

Source reviewed September 9, 2026: Powhatan County's approval and Province Group's project announcement say county water and sewer capacity is available, but neither source publishes a facility withdrawal, consumption, cooling method, or wastewater-service quantity. Preserve those fields as unresolved.

Power

Source reviewed September 9, 2026: Powhatan County approved the 181-acre rezoning for a planned 2-million-square-foot campus, while JLL reports Dominion's initial deployment as 365 MW. County planning material says full-buildout service could be 300-400 MW and that formal authorization awaits site plans and final electrical design. These are planned/anticipated utility-service figures, not energized or IT-load capacity; the dataset's 365-2,400 MW range remains unreconciled.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecy, Public moneyFields with source leads: Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.