Google's Botetourt campus has county zoning and August 2026 grading authorization, with fall 2026 grading expected. County and utility materials disclose planned water and wastewater reservations and attributed infrastructure/incentive terms, but not energized or data-center IT-load capacity.

ProposedconfirmedMedium concern

Site Snapshot

Location
Troutville (Botetourt County), Botetourt County, Virginia
Operator / sponsor
Google
Status / stage
Proposed · utility / power
Scale
Hyperscale (100-999 MW); 900,000 sq ft; 344 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Source reviewed September 9, 2026: Botetourt County reports a $14 million land purchase, a $4 million commitment to county initiatives over five years, discounted land pricing, and a tax-bill stabilization grant. These are attributed project commitments/incentives, not verified public spending; the $14 million dataset cost is not reclassified as public funding.

Water

Source reviewed September 9, 2026: Botetourt County says Google must connect to Western Virginia Water Authority water and sewer, with a Day 1 reservation of no more than 2,000,000 gallons/day of water and 570,000 gallons/day of wastewater capacity. These are planned utility reservations, not measured consumption or final operating use; the county says Google will fund project infrastructure and share of broader improvements.

Power

Source reviewed September 9, 2026: Botetourt County says grading plans and a land-disturbance permit were issued in August 2026, with on-site grading expected in fall 2026 and the first structure expected fit for use in 2028. The dataset's hyperscale label remains unclassified; no reviewed source establishes requested, approved, energized, generation, or data-center IT-load capacity.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.