Proposed-site record

Amazon King George Data Center

Amazon's proposed King George campus was planned for up to 7.25 million square feet on 869 acres, with county records modeling tax revenue and possible infrastructure-grant exposure. Those are planning and fiscal assumptions, not completed spending, public subsidy, requested load, energized capacity, or IT load; water and utility-service records remain unresolved.

Blocked or pausedconfirmedHigh concern

Site Snapshot

Location
King George, Virginia
Operator / sponsor
Amazon
Status / stage
Blocked or paused · blocked / paused
Scale
Unknown; 7,250,000 sq ft; 869 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · Proposed floor area · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

County records contain modeled tax-revenue and infrastructure-grant assumptions for the proposed campus; they do not establish spent money or a final public subsidy. The dataset's $6 billion project-cost lead remains unverified and should not be treated as public funding.

Water

Source review September 9, 2026: the reviewed King George county records describe the proposed campus and its planning assumptions but do not establish a facility water source, cooling method, withdrawal, consumption, or wastewater quantity.

Power

Source review September 9, 2026: county records discuss the proposed Amazon campus and infrastructure-grant assumptions but do not establish requested, approved, energized, generation, or data-center IT-load capacity. The 7.25-million-square-foot figure is project buildout context, not a power measure.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.