Millard County notices establish a conditional-use and gas-infrastructure permitting trail for Joule's AI/HPC campus. The 455-12,000 MW range remains unclassified project/power context; public sources do not establish energized or workload-specific capacity.
ProposedconfirmedHigh concern
Site Snapshot
Location
Millard County, Millard County, Utah
Operator / sponsor
Joule Power
Status / stage
Proposed · utility / power
Scale
455-12000 MW reported; Mega campus (>1,000 MW); 4000 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
Source reviewed September 9, 2026: Joule's public campus page describes a closed-loop, heat-recovery cooling design, while Utah's new data-center water rules require large projects that intend to withdraw at least 75 acre-feet annually to notify the Division of Water Rights and report use. Joule's public materials claim 10,000 acre-feet of senior water rights but do not publish a project withdrawal, consumption, cooling, or wastewater quantity; those remain unresolved.
Source reviewed September 9, 2026: Millard County's public notice and planning minutes identify Joule's conditional-use application for a data center and electrical generating facility; a later county notice identifies a proposed 24-inch natural-gas pipeline development agreement. Joule describes behind-the-meter generation and AI/HPC use, but the dataset's 455-12,000 MW remains an unverified project-scale range, not confirmed generation nameplate, utility load, energized capacity, or data-center IT load.