Proposed-site record

Meta Project Seafox

El Paso confirms the Meta/Wurldwide project is a five-phase hyperscale campus with Phase 1 underway and publishes tiered water-allocation ceilings plus a separate proposed 366 MW generation bridge. The dataset's 1,000 MW remains unclassified project/power context; energized capacity, IT load, measured water and wastewater, workload allocation, and direct public subsidy remain unresolved.

Under constructionconfirmedMedium concern

Site Snapshot

Location
El Paso, Texas
Operator / sponsor
Wurldwide LLC/ Meta/ Blackrock
Status / stage
Under construction · under construction
Scale
1000 MW reported; Mega campus (>1,000 MW); 25,900,000 sq ft; 600 acres; expected online 2029
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area · Target online date

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Source reviewed September 9, 2026: El Paso describes approved land, Chapter 380, and tax-abatement agreements, projected tax revenue, and up to $5 million in non-taxpayer roadway/intersection funding benefiting the wider Northeast community. These are agreements, projections, and infrastructure funding—not verified project spending or a direct subsidy amount attributable to the facility.

Water

Source reviewed September 9, 2026: the City of El Paso's data-center resource hub describes tiered water allocations for the Meta/Wurldwide project, including a Tier III maximum of 2.5 million gallons per day and average of 1.5 million gallons per day at full buildout. These are agreement/allocation ceilings, not measured facility consumption or wastewater discharge; the project's actual phase, source, cooling use, and wastewater quantities remain unresolved.

Power

Source reviewed September 9, 2026: the City of El Paso says the five-phase Meta/Wurldwide project has Phase 1 underway. The city's June 2026 filing describes a separate proposed 366 MW McCloud natural-gas facility intended to serve the project during a bridge period, while its policy framework identifies another 525 MW of Meta-related generation capacity still to be defined. The dataset's 1,000 MW remains unclassified project/power context, not energized or data-center IT load.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.