High-priority Hutto campus with city-published air-cooled water expectations, a developer-advertised private-substation power-availability figure, and a Comptroller-recorded tax-abatement agreement. The 600 MW remains planned power availability rather than confirmed IT load or energized capacity, and the water figures are building-level expectations rather than measured use.
Under constructionconfirmedHigh concern
Site Snapshot
Location
Hutto, Williamson County, Texas
Operator / sponsor
Unknown operator
Status / stage
Under construction · under construction
Scale
Hyperscale (100-999 MW); 160 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
Source reviewed September 9, 2026: the Texas Comptroller records an effective July 21, 2023 Hutto tax-abatement agreement for Hutto Data Center Campus Power LLC c/o Skybox Datacenters, with a stated $10 billion minimum combined investment commitment over 10 years. This is a tax-abatement agreement and investment commitment, not proof of public spending or realized investment.
Source reviewed September 9, 2026: Hutto's utility FAQ says the data centers being built in Hutto are air-cooled, with each building expected to use around 500 gallons per day indoors and up to 15,000 gallons per day for irrigation across all three buildings; it says this is after initial cooling/fire-system filling. These are city-published expectations for the buildings, not a measured withdrawal, cooling-water consumption, or wastewater-service quantity for this record alone.
Source reviewed September 9, 2026: Skybox's PowerCampus Austin page advertises up to 600 MW of power availability supported by a private onsite substation, while the Texas Comptroller records Hutto Data Center Campus Power LLC's Chapter 380/381 tax-abatement agreement and $10 billion minimum combined investment commitment. The 600 MW is advertised planned power availability, not confirmed requested, approved, energized, generation, or data-center IT-load capacity; the dataset record has no numeric capacity value to reclassify.
Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.