Proposed-site record

MSB Global Services Matrix Data Center

The Texas Comptroller's agreement record identifies SSDC1, LLC as the counterparty and documents a 1,677-acre land conveyance with phased 800/1,200/1,000 MW minimum capacity obligations. MSB's developer materials add a 100 MW critical-IT-load-per-building design claim, but the dataset's 3,000 MW remains planned campus/power context rather than confirmed energized facility IT load.

ProposedconfirmedMedium concern

Site Snapshot

Location
Sulphur Springs, Hopkins County, Texas
Operator / sponsor
Unknown operator
Status / stage
Proposed · utility / power
Scale
3000 MW reported; Mega campus (>1,000 MW); 1677 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Source reviewed September 9, 2026: The Texas Comptroller records a $16.77 million City of Sulphur Springs land-conveyance agreement to SSDC1, LLC, with a May 9, 2025 effective date and data-center construction obligations. This is a land transaction/agreement value, not spent money or a grant, and remains separate from the dataset's project-cost field.

Water

Source reviewed September 9, 2026: MSB Global describes direct-to-chip liquid cooling and a proposed zero-water design, but the reviewed developer materials do not provide a measured withdrawal, consumption, cooling, or wastewater quantity. Treat this as a design claim, not a verified water outcome.

Power

Source reviewed September 9, 2026: The Texas Comptroller's agreement record, effective May 9, 2025, requires minimum data-center capacities of 800 MW in Phase 1, 1,200 MW in Phase 2, and 1,000 MW in Phase 3; MSB separately describes 100 MW of critical IT load per building. The dataset's 3,000 MW remains planned campus/power context, not proof that all phases or buildings are energized or operating.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.