Comanche Circle Data Centers

Comanche Circle has an approved Hood County concept plan but still requires later site-development review. Proposed private wells, private wastewater treatment, and the separate 2 GW Tolar generation plan are infrastructure context; NRG's generation permit withdrawal leaves the dataset's 600 MW as unclassified project/power context rather than confirmed facility service or IT load.

Under constructionconfirmedHigh concern

Site Snapshot

Location
Tolar, Hood County, Texas
Operator / sponsor
Sailfish Digital Ventures
Status / stage
Under construction · under construction
Scale
600 MW reported; Mega campus (>1,000 MW); 5,500,000 sq ft; 2000 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

No public funding record attached yet. Local subsidy, tax-abatement, land, bond, and utility records need follow-up.

Water

Source reviewed September 9, 2026: KERA reports the Hood County concept plan involves proposed private groundwater wells and a private wastewater plant, while later approval reporting says water, wastewater, drainage, and environmental engineering remain for site-development review. These are proposed service concepts, not a measured withdrawal, service allocation, or wastewater quantity.

Power

Source reviewed September 9, 2026: KERA reports NRG withdrew the application for the proposed 2 GW Tolar Power Center on June 18, 2026; the related Comanche Circle data-center concept remains active. The dataset's 600 MW remains unclassified project/power context, and the withdrawn generation proposal is not energized capacity or data-center IT load.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecy, Public moneyFields with source leads: Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.