Proposed-site record

AREP PowerHouse Grand Prairie

PowerHouse Data Centers' Grand Prairie campus is under construction and the developer publishes 810 acres, 8.5 million square feet, and up to 1.8 GW of maximum utility power with Q1 2027 delivery. The 1.8 GW remains planned utility/project context, not energized or IT-load capacity; facility water, wastewater, workload allocation, and public funding remain unresolved.

Under constructionconfirmedMedium concern

Site Snapshot

Location
Midlothian, Ellis County, Texas
Operator / sponsor
PowerHouse Data Centers
Status / stage
Under construction · under construction
Scale
1800 MW reported; Mega campus (>1,000 MW); 8,500,000 sq ft; 810 acres; expected online 2027
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area · Target online date

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Source reviewed September 9, 2026: the source dataset reports a $72 million project_cost field, but the reviewed developer and Texas permit sources do not identify whether it is spending, investment, land, infrastructure, or public funding. Preserve it as an attributed dataset lead rather than a verified subsidy or expenditure.

Water

Source reviewed September 9, 2026: PowerHouse's project page describes the campus scale and sustainability program but does not publish a facility-specific water withdrawal, consumption, cooling, or wastewater quantity. Preserve water use as unresolved.

Power

Source reviewed September 9, 2026: PowerHouse Data Centers lists 1.8 GW as maximum utility power for its 810-acre, 8.5-million-square-foot campus and gives Q1 2027 delivery. This is developer-stated planned utility/project capacity, not energized or data-center IT load; phase-specific delivery and interconnection evidence remain unresolved.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.