Walterboro's proposed Eagle Rock campus remains an early-stage, speculative nine-building proposal. A county-hosted planning packet reproduces developer statements of about 12,000 gallons/day, closed-loop cooling, and 1,000 MW electricity demand; those are attributed planning estimates, not permits, measured use, energized capacity, or IT load.
Proposedconfirmed
Site Snapshot
Location
Walterboro, Colleton County, South Carolina
Operator / sponsor
Eagle Rock Partners
Status / stage
Proposed · approval / land-use
Scale
1,000 MW reported; Mega campus (>1,000 MW); 859 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
The project article reports a developer-stated $6 billion project context, not completed spending or a public subsidy. The reviewed materials do not establish itemized incentives, abatements, public infrastructure contributions, or ratepayer charges.
Source reviewed September 9, 2026: a project article reproduced in an Oconee County planning packet attributes an approximately 12,000-gallons-per-day estimate and closed-loop cooling description to Eagle Rock co-founder Ken Loeber. The estimate is a developer statement, not a permit, service agreement, measured use, or final withdrawal/wastewater quantity; preserve those distinctions.
Source reviewed September 9, 2026: the same project article attributes a 1,000 MW electricity estimate to Eagle Rock's co-founder and says the proposal was speculative without a specific tenant, while the related 2,200 MW Canadys generation project remained in permitting. The dataset's 1,000 MW remains proposed project/utility-demand context, not confirmed requested, approved, energized, generation, or data-center IT-load capacity.
Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.