Proposed-site record

Shippingport Bruce Mansfield Data Center/ Project Phoenix

High-priority former Bruce Mansfield site proposal with a dated municipal conditional-use trail and a separate power-conversion program. Public materials still do not establish facility IT load, energized service, water quantity, or workload allocation.

Under constructionconfirmedHigh concern

Site Snapshot

Location
Shippingport, Beaver County, Pennsylvania
Operator / sponsor
Aligned Data Centers
Status / stage
Under construction · under construction
Scale
2,550-3,600 MW reported; Mega campus (>1,000 MW); 2,000,000 sq ft; 543 acres; expected online 2029
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area · Target online date

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Source dataset project_cost field reports $10 billion; public funding records still need local review.

Water

Source review September 9, 2026: the dataset describes closed-loop cooling with water as the cooling source, but the reviewed Shippingport Borough conditional-use notice and project materials do not publish a withdrawal, consumption, cooling, or wastewater quantity. Water permits and service records remain open.

Power

Source review September 9, 2026: Shippingport Borough published a March 31, 2026 conditional-use hearing notice for Aligned Data Centers. Shippingport Industrial Park separately describes a coal-to-gas conversion, a 2.5+ GW power delivery target, and a gas lateral under construction; these are project-generation/grid context, not confirmed data-center IT load or energized capacity. The dataset's 2,550-3,600 MW remains unclassified for the data-center facility.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.