Proposed-site record

Logistix Data Center

High-priority Hamilton Innovation Center proposal at 1380 University Boulevard. The January 2026 feasibility result distinguishes Logistix's 240 MW request from only 45 MW deliverable within 24 months; the project remains proposed and paused, with water and final utility terms unresolved.

ProposedconfirmedHigh concern

Site Snapshot

Location
Hamilton, Butler County, Ohio
Operator / sponsor
Logistix Property Group
Status / stage
Proposed · approval / land-use
Scale
200-240 MW reported; Hyperscale (100-999 MW); about 310,640-320,000 sq ft; 29 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Source reviewed September 9, 2026: city and local reporting describe a possible $1 billion-plus developer-funded project and the city's prior $65,000 land sale. No reviewed source establishes a subsidy, tax abatement, completed spending, or final utility-cost allocation.

Water

Source reviewed September 9, 2026: the reviewed city feasibility and planning trail does not disclose a water source, cooling method, withdrawal permit, wastewater capacity, or operating-use quantity. Those remain unresolved.

Power

Source reviewed September 9, 2026: Hamilton's city-commissioned feasibility study found the site could deliver only 45 MW within 24 months against Logistix's 240 MW request, and the developer paused further study while evaluating next steps. These are requested and near-term deliverability figures, not approved, energized, generation, or data-center IT-load capacity.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.