Project Jupiter

Media Monitoring lead with medium location confidence. Use the linked sources to verify status, public money, NDA/secrecy, water, and power details before treating this as a fully documented local record.

Under constructionconfirmedHigh concern

Site Snapshot

Location
Santa Teresa, Doña Ana County, New Mexico
Operator / sponsor
Open AI/Oracle
Status / stage
Under construction · under construction
Scale
700 MW reported; Mega campus (>1,000 MW); 3,000,000 sq ft; 1400 acres; expected online 2026
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area · Target online date

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Mixed workloadsPartially Verified

Oracle's March 2026 permit comments identify it as Project Jupiter's tenant and describe an AI data-center campus; its July 2026 update adds current construction and onsite-workforce context, while related reporting connects the site to OpenAI. These sources do not establish whether the capacity is for frontier training, inference, traditional cloud, or some mix.

Oracle's permit comments, July 2 permit letter, water-use statement, June 2026 power-plan update and July 2026 progress update support tenant, AI-campus, cooling-plan, power-design, staffing and development-status context, not a measured workload allocation. The reported onsite workforce is construction/status context. Do not allocate the 700 MW reported facility scale, the 2.45 GW Bloom/Oracle power figure, or the $165B project-cost claim to any specific compute workload without a stronger source.

Sources reviewed; planned use partly identified · Reviewed 2026-09-09Training/inference: unknown · class: centralizedData Center Dynamics: Oracle revealed as tenant of Project Jupiter data center campus in New MexicoOracle: Oracle Support Letter to New Mexico Improvement BoardOracle Cloud Infrastructure: The Facts About Project Jupiter's Water UsageOracle: Public Review Opens for Updated Project Jupiter Power PlanOracle: Project Jupiter Will Bring More Than $4.7 Billion to New Mexico and Hundreds of Jobs for State ResidentsOracle: Oracle comments on updated Project Jupiter air permit

Public Money

Source dataset project_cost field reports $165 billion; public funding records still need local review.

Water

Source reviewed September 9, 2026: Oracle's updated Project Jupiter power-plan announcement says the fuel-cell microgrid is expected to avoid public drinking water for power generation and data-center cooling and requires only minimal water for power-generation startup fill. The company statement does not publish a facility withdrawal, consumption, cooling, service, or wastewater quantity; those records remain open.

Power

Source reviewed September 9, 2026: Oracle says an updated air-quality application replaces the earlier gas-turbine and diesel design with a Bloom fuel-cell microgrid. Bloom separately describes up to 2.45 GW of fuel-cell capacity for the campus. These are planned onsite-generation/project-power figures, not confirmed utility load, energized capacity, or data-center IT load; tariff, interconnection, fuel-supply, and ratepayer records remain separate questions.

Missing WaterFields with source leads: NDA / secrecy, Public money, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.