Rocklocker withdrew the Kalkaska Go proposal in November 2025 after public opposition to a prospective 1,440-acre state-land campus. Public project material described a 1-gigawatt concept with onsite generation and carbon capture, but no utility, interconnection, water, wastewater, energized, or IT-load record was established; the dataset's 1,000 MW remains historical proposal context.
Blocked or pausedconfirmedHigh concern
Site Snapshot
Location
Kalkaska Township, Kalkaska County, Michigan
Operator / sponsor
Unknown operator
Status / stage
Blocked or paused · blocked / paused
Scale
1000 MW reported; Mega campus (>1,000 MW); 1440 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
No public funding record attached yet. Local subsidy, tax-abatement, land, bond, and utility records need follow-up.
Water
Water source, cooling method, withdrawal permits, and wastewater impacts need local sourcing.
Power
Source reviewed September 9, 2026: Rocklocker and Kalkaska Go described a proposed 1-gigawatt campus with an onsite natural-gas power plant and carbon-capture concept, but the developer withdrew the proposal in November 2025 after public opposition and did not acquire or develop the public-land site. The dataset's 1,000 MW remains historical proposal/project-power context, not confirmed requested, approved, energized, generation, or data-center IT-load capacity.
Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.