Proposed-site record

Howell Data Center

Howell's proposal remains blocked or paused after the rezoning and text-amendment withdrawal. The developer reports up to 1 MGD for an initial building and the township packet contains a 187.5 MW draft campus limit, but neither establishes final utility service, measured water use, energized capacity, IT load, or operating status.

Blocked or pausedconfirmedHigh concern

Site Snapshot

Location
Fowlerville, Livingston County, Michigan
Operator / sponsor
Santec Consulting/Meta
Status / stage
Blocked or paused · blocked / paused
Scale
Hyperscale (100-999 MW); 1077 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

CBS Detroit reports that the Howell Township developer withdrew the proposed 1,000-acre data-center application at the request of the township and applicant, with possible reevaluation. A September 2025 township memo describes the proposed data-processing facility and its construction and operations staffing, while the reviewed public reporting describes a proposed AI data center and reported Meta connection; none establishes a facility-specific workload, customer, hardware or training/inference split.

Santec Consulting/Randee and the reported Meta relationship remain development/end-user leads, not proof of a facility workload allocation. Howell Township minutes record the applicants' withdrawal of the text-amendment request, confirming a permitting-status update rather than a permanent abandonment or workload disclosure. AI wording in local coverage is a project description; it does not establish training, inference, hardware or workload MW.

Sources reviewed; workload unresolved · Reviewed 2026-09-09Training/inference: unknown · class: unknownCBS Detroit: Howell Township data center developer withdraws project applicationWDIV / ClickOnDetroit: Developer pulls rezoning request for proposed AI data center in Howell TownshipHowell Township: Memo: Howell Township proposed data processing facilityHowell Township: Howell Township Board minutes — Stantec/Randee withdrawal

Water

Source reviewed September 9, 2026: the project's water FAQ says the current plan requests up to 1 million gallons per day for the initial building, while actual demand depends on cooling technology and weather. This is a developer planning ceiling, not measured use, a final service agreement, a withdrawal permit, or wastewater capacity; the same FAQ describes an aquifer study and multiple modeled scenarios.

Power

Source reviewed September 9, 2026: Howell Township's March 31, 2026 planning packet proposes maximum campus power usage of 187.5 MW and bars onsite generation other than permitted renewables. Those are draft zoning limits, not a Howell project request, interconnection approval, energized capacity, generation capacity, or data-center IT load; the proposal's utility status remains unresolved after the application withdrawal.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.