Howell's proposal remains blocked or paused after the rezoning and text-amendment withdrawal. The developer reports up to 1 MGD for an initial building and the township packet contains a 187.5 MW draft campus limit, but neither establishes final utility service, measured water use, energized capacity, IT load, or operating status.
Blocked or pausedconfirmed
Site Snapshot
Location
Fowlerville, Livingston County, Michigan
Operator / sponsor
Santec Consulting/Meta
Status / stage
Blocked or paused · blocked / paused
Scale
Hyperscale (100-999 MW); 1077 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
CBS Detroit reports that the Howell Township developer withdrew the proposed 1,000-acre data-center application at the request of the township and applicant, with possible reevaluation. A September 2025 township memo describes the proposed data-processing facility and its construction and operations staffing, while the reviewed public reporting describes a proposed AI data center and reported Meta connection; none establishes a facility-specific workload, customer, hardware or training/inference split.
Santec Consulting/Randee and the reported Meta relationship remain development/end-user leads, not proof of a facility workload allocation. Howell Township minutes record the applicants' withdrawal of the text-amendment request, confirming a permitting-status update rather than a permanent abandonment or workload disclosure. AI wording in local coverage is a project description; it does not establish training, inference, hardware or workload MW.
Source reviewed September 9, 2026: the project's water FAQ says the current plan requests up to 1 million gallons per day for the initial building, while actual demand depends on cooling technology and weather. This is a developer planning ceiling, not measured use, a final service agreement, a withdrawal permit, or wastewater capacity; the same FAQ describes an aquifer study and multiple modeled scenarios.
Source reviewed September 9, 2026: Howell Township's March 31, 2026 planning packet proposes maximum campus power usage of 187.5 MW and bars onsite generation other than permitted renewables. Those are draft zoning limits, not a Howell project request, interconnection approval, energized capacity, generation capacity, or data-center IT load; the proposal's utility status remains unresolved after the application withdrawal.
Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.