Proposed-site record

Related Digital/The Barn

Related Digital's The Barn is an under-construction Saline Township campus for Oracle and its customer OpenAI. The developer's current project page distinguishes closed-loop cooling from a proposed treated-sanitary-wastewater discharge under EGLE permit MI0060445; neither source establishes cooling water quantity or data-center IT load.

Under constructionconfirmedHigh concern

Site Snapshot

Location
Saline, Washtenaw County, Michigan
Operator / sponsor
Related Digital/Open AI/Oracle
Status / stage
Under construction · under construction
Scale
1400 MW reported; Mega campus (>1,000 MW); 2,200,000 sq ft; 575 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Water

Source reviewed September 9, 2026: Related Digital says The Barn uses closed-loop air cooling rather than evaporative cooling, with ongoing water use described as comparable to a normal office building. Its project page also identifies EGLE permit MI0060445 for treated sanitary wastewater from restrooms and sinks, explicitly separating that discharge from cooling-system water and industrial coolant. No reviewed source publishes a cooling withdrawal, consumption, or wastewater-service quantity.

Power

Source reviewed September 9, 2026: the Michigan Public Service Commission's December 18, 2025 conditional approval describes a 1,383 MW contracted data-center load for Green Chile Ventures in Saline Township and a matching 1,383 MW energy-storage obligation; Related Digital's project page describes a campus with more than one gigawatt of gross capacity. These are contracted utility-service and project-scale figures, not proof of energized capacity or data-center IT load, and the 1,400 MW dataset value remains a rounded project-context figure.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.