Proposed-site record

Panattoni Project Cannoli

High-priority Google/Panattoni Project Cannoli proposal in Van Buren Township. Township planning records document the preliminary site-plan path for three data-processing buildings and a substation; the campus-scale power lead remains separate from DTE's broader generation partnership and from confirmed IT load.

ProposedconfirmedHigh concern

Site Snapshot

Location
Van Buren Township, Wayne County, Michigan
Operator / sponsor
Google
Status / stage
Proposed · approval / land-use
Scale
1000-2700 MW reported; Mega campus (>1,000 MW); 800,000 sq ft; 282 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

No public funding record attached yet. Local subsidy, tax-abatement, land, bond, and utility records need follow-up.

Water

Source reviewed September 9, 2026: Van Buren Township's preliminary site-plan materials identify three data-processing buildings, a network-service building, a water-services building, and stormwater ponds, but the reviewed public record does not establish a water-service quantity, cooling withdrawal, consumption, or wastewater capacity.

Power

Source reviewed September 9, 2026: Van Buren Township's February 11, 2026 agenda records the preliminary site-plan request for three data-processing buildings and a substation; Panattoni describes a Fortune 50 cloud/data-processing use, while reporting identifies Google as the end user. DTE's separate 2.7 GW clean-resource partnership is grid-generation context, not this campus's load. The dataset's 1,000-2,700 MW remains proposed project/power context, not confirmed requested, approved, energized, generation, or data-center IT-load capacity.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecy, Public moneyFields with source leads: Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.