High-priority Greensburg / Decatur County proposal from Jumping Bison LLC. The city-approved 10-year, 60% real-property abatement and two-phase investment plan improve public-money provenance, while utility capacity, water, and cooling remain unresolved.
ProposedconfirmedHigh concern
Site Snapshot
Location
Greensburg, Decatur County, Indiana
Operator / sponsor
Jumping Bison LLC
Status / stage
Proposed · approval / land-use
Scale
Hyperscale (100-999 MW); 550 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
Source reviewed September 9, 2026: Greensburg City Council approved a 10-year, 60% real-property tax abatement for Jumping Bison LLC, and WRBI reports two phases of about $400 million each. The abatement is an approved incentive; it is not a spending total or proof of the value of any subsidy without the underlying schedule and fiscal records.
Source reviewed September 9, 2026: the reviewed city and public project trail does not disclose a water source, cooling method, withdrawal permit, wastewater capacity, or operating-use quantity. Those remain unresolved.
Source reviewed September 9, 2026: public utility trackers associate the proposed Greensburg project with Duke Energy and report about 50 MW, but no reviewed utility filing establishes requested, approved, energized, generation, or data-center IT-load capacity. The 550-acre site and two-phase plan remain project context.