Proposed-site record

Agincourt

Valparaiso's official statement says no data-center project was pending before the city; Agincourt's option and due-diligence path required future power, water, environmental, and rezoning work. The dataset's scale remains unclassified and the proposal is blocked or paused.

Blocked or pausedconfirmedMedium concern

Site Snapshot

Location
Valparaiso, Porter County, Indiana
Operator / sponsor
Unknown operator
Status / stage
Blocked or paused · blocked / paused
Scale
Hyperscale (100-999 MW); 2,400,000 sq ft; 248 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

No public funding record attached yet. Source reviewed September 9, 2026: Valparaiso says Agincourt proposed an option for approximately 180 acres, deposited $50,000 with $10,000 nonrefundable, and offered just over $9 million for the land; the city says no tax abatement or other economic incentive was requested. These are reported option and land-purchase terms, not public spending or subsidy.

Water

Source reviewed September 9, 2026: Valparaiso's mayoral statement says Agincourt still had to establish water availability with Valparaiso City Utilities and protect existing test wells. No water-service quantity, cooling withdrawal, consumption, permit, or wastewater capacity is disclosed.

Power

Source reviewed September 9, 2026: Valparaiso's official statement says Agincourt was conducting due diligence and had to confirm sufficient power with NIPSCO; it also says no data-center project was pending before the city and rezoning would still be required. The dataset's 2,400,000-square-foot scale remains unclassified project context, not confirmed requested, approved, energized, generation, or IT-load capacity.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecy, Public moneyFields with source leads: Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.