Meta's Project Domino is a phased Lebanon campus with a city development-plan record, a water/wastewater pre-allocation memorandum, and company-stated 1 GW planned capacity. The MW figure remains separate from energized and IT-load capacity; facility water quantities and public-money accounting remain unresolved.
Under constructionconfirmedMedium concern
Site Snapshot
Location
Lebanon, Boone County, Indiana
Operator / sponsor
Meta
Status / stage
Under construction · under construction
Scale
1000 MW reported; Mega campus (>1,000 MW); 1500 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
Source reviewed September 9, 2026: Meta describes more than $10 billion of planned project investment, more than $120 million toward critical water and other public infrastructure, and $1 million annually for 20 years to a Boone County community fund. These are company-stated investment, infrastructure, and donation commitments, not recorded spending or a public subsidy amount.
Source reviewed September 9, 2026: Lebanon Utilities approved a Project Domino water-supply and wastewater-capacity pre-allocation memorandum, while the city's development-plan review still requested phased average/peak demands, wastewater flows, connection proportions, and infrastructure easements. Meta says it will pay the full cost of service, but no facility withdrawal, consumption, or wastewater quantity is published.
Source reviewed September 9, 2026: Meta describes the Lebanon campus as designed to deliver 1 GW once operational and to support AI workloads and core products. The city's 2025 development-plan record documents 12 data-center buildings and a phased construction plan. The dataset's 1,000 MW remains planned facility/project context, not confirmed energized or IT-load capacity.