Amazon's Hobart campus has approved local rezoning and a documented NIPSCO/MISO power pathway. The 2,400 MW contract ramp and separate 1,500 MW transmission project remain planned utility-service context, not energized or IT-load capacity; facility water, wastewater, and public-money amounts remain unresolved.
Under constructionconfirmedHigh concern
Site Snapshot
Location
Hobart, Lake County, Indiana
Operator / sponsor
Amazon
Status / stage
Under construction · under construction
Scale
2400 MW reported; Mega campus (>1,000 MW); 900 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
Source reviewed September 9, 2026: Hobart's rezoning materials say water is available and the regional lift station could be upgraded for sanitary sewer, but the city materials and utility records reviewed do not disclose a facility withdrawal, consumption, cooling method, or wastewater-service quantity. Preserve those fields as unresolved.
Source reviewed September 9, 2026: the Indiana Utility Regulatory Commission approved an Amazon/NIPSCO service arrangement ramping to 2,400 MW by the end of 2032, and MISO lists a separate approved 1,500 MW New Hobart Load Addition. These are utility-service and transmission-planning figures, not energized capacity or data-center IT load; Hobart's rezoning and permit materials remain separate approvals.
Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.