Proposed-site record

CyrusOne

Media Monitoring lead with high location confidence. Use the linked sources to verify status, public money, NDA/secrecy, water, and power details before treating this as a fully documented local record.

Under constructionconfirmedHigh concern

Site Snapshot

Location
Waverly/ Talkington Twp, Sangamon County, Illinois
Operator / sponsor
Unknown operator
Status / stage
Under construction · under construction
Scale
632 MW reported; Hyperscale (100-999 MW); 250,000 sq ft; 280 acres; expected online 2027
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area · Target online date

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Water

Source reviewed September 9, 2026: Sangamon County's CyrusOne project page and the developer's community FAQ describe a closed-loop, air-cooled design with water use expected to be comparable to a typical office building rather than significant cooling withdrawals. The water service agreement and final site-plan mechanical narrative remain unresolved; the dataset's water-source field is not treated as proof of a measured quantity.

Power

Source reviewed September 9, 2026: Sangamon County records the county board's April 7, 2026 approval of the proposed CyrusOne campus, while public project materials describe roughly 600-634 MW at full build. The dataset's 632 MW remains proposed project-scale context; utility service, interconnection, energized capacity, generation, and data-center IT load remain unverified.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.