Proposed-site record

Hogansville Data Center

The Hogansville / Project West proposal has a documented February 2026 90-day moratorium covering the Hightower Road property, and the city has published draft data-center zoning amendments. The reviewed sources do not establish whether a moratorium remains in effect as of September 9, 2026. The 600 MW and reported MEAG cost figures remain proposed utility and planning context, not energized or IT-load capacity or verified public spending.

ProposedinferredHigh concern

Site Snapshot

Location
Hogansville, Troup County, Georgia
Operator / sponsor
Unknown operator
Status / stage
Proposed · approval / land-use
Scale
600 MW reported; Hyperscale (100-999 MW); 437 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Source reviewed September 9, 2026: GPB reported a MEAG study estimating approximately $300 million in local power-system cost and $153.75 million borne by the customer. These are attributed planning/cost-allocation figures, not verified spending, public subsidy, or an executed rate arrangement.

Water

Source reviewed September 9, 2026: Hogansville's February 2, 2026 council minutes document a 90-day all-inclusive data-center moratorium applying to the Hightower Road property, while the city's comprehensive-plan materials identify the former spray-field/wastewater site. Neither source discloses a facility withdrawal, consumption, cooling method, or wastewater-service quantity.

Power

Source reviewed September 9, 2026: GPB reported that MEAG studied how a 600 MW load could be brought online, while the February city minutes record a temporary moratorium and the city has published draft data-center zoning amendments. The 600 MW remains proposed load context; no approved, energized, generation, or data-center IT-load capacity is established.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.