Water
Source reviewed September 9, 2026: Columbia County's July 23, 2026 partnership notice names protections for the local water supply, and its August 26 announcement describes closed-loop cooling and a ban on private wells for the county data-center project. Neither source discloses a Pumpkin-specific withdrawal, consumption, cooling, service, or wastewater quantity. Preserve the dataset's closed-loop description as a design commitment, not measured performance.
Power
Source reviewed September 9, 2026: Columbia County approved Pumpkin's zoning change on February 4, 2026 but required a Georgia Power letter showing it could meet the proposed site's power needs before construction. The county's July 23 partnership notice says Google committed to pay associated energy costs and that ratepayers would not bear additional infrastructure, transmission, or capacity expenses; the August 26 MOU announcement identifies Kinetic Infrastructure Solutions, an Alphabet subsidiary, as the private counterparty for the county data-center project. The dataset's 500 MW remains unclassified project/power context, not confirmed requested, approved, energized, generation, or data-center IT-load capacity.