Sentinel Grove/Project Jarvis was a proposed 1,218-acre, 15-million-square-foot campus whose land-use application was voluntarily withdrawn on February 26, 2026. The 1,000 MW and reported water allocation remain historical project context; no approved, energized, IT-load, facility-water, wastewater, workload, or public-funding amount is established.
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
Source reviewed September 9, 2026: public reporting attributes approximately $13.5 billion to the proposed first 1,000 MW buildout and $15 million to the land purchase by Epic Estates 68 LLC. These are private project/investment and land-transaction figures, not verified public spending or subsidy amounts.
Source reviewed September 9, 2026: current public reporting says the proposed Sentinel Grove parcel had a reported 2.2 million-gallons-per-day allocation, but that figure is not a facility withdrawal or consumption measurement. The reviewed sources do not establish cooling method, wastewater service, or project-specific water use; preserve those fields as unresolved.
Source reviewed September 9, 2026: the Sentinel Grove/Project Jarvis land-use application was voluntarily withdrawn on February 26, 2026 while Florida legislation was advancing. The proposed 1,000 MW remains historical project-scale context, not approved, energized, generation, or data-center IT-load capacity; the parcel remains agricultural and a refiled application is not documented.
Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.