Proposed-site record

Imperial Data Center

Media Monitoring lead with high location confidence. Use the linked sources to verify status, public money, NDA/secrecy, water, and power details before treating this as a fully documented local record.

Under constructionconfirmedHigh concern

Site Snapshot

Location
Imperial, California
Operator / sponsor
Imperial Valley Computer Manufacturing, LLC/ Google (unconfirmed)
Status / stage
Under construction · under construction
Scale
330 MW reported; Hyperscale (100-999 MW); 950,000 sq ft; 74 acres; expected online 2027
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area · Target online date

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Water

Source reviewed September 9, 2026: the City of Imperial's project notice identifies the county-approved or approval-in-process complex but does not establish delivered water. The developer describes zero Colorado River water and reclaimed-water design assumptions, while public reporting describes a disputed request for approximately 287 million gallons annually; the water agreement, final permit posture, and operating quantity remain unresolved.

Power

Source reviewed September 9, 2026: the City of Imperial identifies a 330 MW data center, a separate 330 MW emergency-generator building, and an 862 MWh energy-storage system. The developer says the 330 MW grid supply connects to Imperial Irrigation District through an onsite substation and that natural-gas generators are emergency backup only. These are planned utility and backup-power figures, not confirmed energized or data-center IT-load capacity.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.