Proposed-site record

Project Blue Tucson

High-priority Project Blue / Beale Infrastructure data-center project near the Pima County Fairgrounds. Tucson rejected the annexation/development agreement in August 2025, but the county-side project continued through land, water-well, and electric-service pathways, making status, water, power, and public-money tracking especially important.

Under constructionconfirmedHigh concern

Site Snapshot

Location
Tucson, Pima County, Arizona
Operator / sponsor
Beale Infrastructure
Status / stage
Under construction · under construction
Scale
Unknown; 290 acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Source lead: dataset reports a $3.6 billion project; Pima County's FAQ identifies Project Blue as a billion-dollar economic development proposal, and local reporting ties the project to county land-sale negotiations. Land-sale, incentive, tax, utility-cost, and public-benefit records still need review.

Water

Source reviewed September 9, 2026: Pima County's Project Blue FAQ describes a proposed 290-acre campus and the County's April 23, 2026 progress memo lists four issued water-capacity-letter records alongside active permitting. Tucson's July 2025 fact sheet gives projected average annual reclaimed-water allocations of 440 AFY for the primary initial phase, 870 AFY for primary full build, and 1,040 AFY if the secondary project reaches full build. These are projected allocation volumes that may vary, not measured consumption or a facility-wide service guarantee. The County's June 17, 2025 project announcement describes a developer commitment to use reclaimed water in industrial systems and replenish consumptive losses; AZPM reported approval of wells tied to the project with potential use up to 31 million gallons annually. Final well withdrawal, cooling, wastewater, and operating-use quantities remain unresolved.

Power

Source reviewed September 13, 2026: the Arizona Corporation Commission says it approved TEP's special electric-service agreement for Project Blue and describes an initial anticipated load of 286 MW, with additional generation beyond that amount to be paid by the data center. TEP's agreement summary says the deal includes minimum monthly bills, financial security, and a termination fee if the project does not meet its obligations. These are approved planned utility terms, not proof of energized capacity, actual payments, or data-center IT load; the dataset's project scale remains unclassified.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

NDA / Secrecy

No NDA reported

Missing NDA / secrecyFields with source leads: Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.