High-confidence Bessemer proposal with a revised municipal plan, proposed substation, and unresolved water and utility impacts. The 1,200 MW figure remains proposed project-scale/power-demand context rather than confirmed IT load or energized capacity.
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Proposed floor area · Site area · Target online date
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
QTS describes a Bessemer campus in development; WBRC links it to Project Marvel. Bessemer's official notice records an updated planning and development framework after public feedback. A public mirror of the February 2026 WBRC-uploaded exhibit shows a proposed site plan with substations and stormwater detention, but the reviewed sources do not identify a customer, specific workload, or training/inference split.
QTS is identified as the developer; that does not establish a facility workload or customer allocation. Bessemer's undated official notice records an updated planning framework in response to public feedback, but does not disclose the resulting plan details or workload. The public exhibit mirror is a site-plan lead, not a primary municipal publication and not workload evidence. The reported 1,200 MW project figure is not a workload allocation. Workload capacity remains unknown.
Source reviewed September 9, 2026: the dataset's $14.5 billion figure and WBRC-reported roughly $75 million per year are project-cost and projected local-tax-impact context, not recorded spending or a subsidy award. Alabama Revenue's Chapter 9B guidance confirms that qualifying data-processing centers may receive state and local tax abatements through a local resolution and executed agreement, but the reviewed state guidance does not establish that Project Marvel received one. A project-specific resolution, abatement agreement, infrastructure commitment, and public-cost record remain unresolved.
Source review: the Bessemer project materials and environmental-advocacy filings describe substantial potential water demand, including a reported request for at least 2 million gallons per day, but no reviewed permit or executed service agreement establishes a final withdrawal, consumption, cooling, or wastewater quantity.
Source reviewed September 9, 2026: the City of Bessemer describes revised planning for the proposed campus, and reporting on the February 2026 exhibit describes 18 buildings across an expanded site with a proposed substation. The dataset's 1,200 MW remains proposed project-scale/power-demand context, not confirmed requested, approved, energized, generation, or data-center IT-load capacity.