Edged's proposed 8 MW Project Gateway in Prichard remains a proposal under evaluation. The developer describes waterless cooling and self-funded power infrastructure, while August 2026 reporting says a proposed temporary city moratorium could affect the project; enacted status, utility service, facility IT load, measured water, wastewater, workload allocation, and public funding remain unresolved.
ProposedconfirmedHigh concern
Site Snapshot
Location
Prichard, Mobile County, Alabama
Operator / sponsor
Edged
Status / stage
Proposed · approval / land-use
Scale
8 MW reported; Small (0-10 MW); expected online 2026
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · MW type not established · Target online date
Compute Workload
This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.
Undisclosed / unknownUnknown
No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.
Workload classification remains unknown in the reviewed record.
Data Fields
Source leads point to attached records or reporting. They still need field-level review before being treated as verified evidence.
Source reviewed September 9, 2026: Project Gateway's current page attributes a $93 million private investment and says Edged would pay for its own power and equipment upgrades. These are developer-stated investment and cost commitments, not verified public spending, subsidy, or completed infrastructure payment; local tax-abatement, permit, road, and agreement records remain unresolved.
Source reviewed September 9, 2026: Project Gateway's current project page describes Edged's proposed closed-loop waterless cooling and says daily cooling would use zero community water, with an attributed comparison of about 23 million gallons saved annually. These are developer design and projected-comparison claims, not measured withdrawal, consumption, wastewater, or permit quantities; local service and permit records remain unresolved.
Source reviewed September 9, 2026: Project Gateway's current page describes an 8 MW proposed facility and says the developer would manage and pay for its power use and equipment upgrades. Data Center Dynamics reported on August 10, 2026 that Prichard was considering a temporary moratorium that could affect the project, but the reviewed sources do not establish enacted-moratorium terms, utility interconnection, energized capacity, or data-center IT load.