Proposed-site record

Stratos Project

Kevin O'Leary's Utah-backed Stratos Project has become one of the country's highest-profile data center fights, drawing criticism over fast-track approval, land scale, power demand, water, and transparency.

ProposedconfirmedHigh concern

Site Snapshot

Location
Box Elder County, Utah
Operator / sponsor
O'Leary Digital / O'Leary Ventures
Status / stage
Proposed · proposal
Scale
Originally described as about 40,000 acres; later reduced to about 20,000 acres with roughly 10,000 developable acres
Reported project context; confirm whether any MW figure is requested, approved, energized, IT load, generation, or ultimate buildout before comparing it with another record.Capacity reading: Project-scale context · Site area

Compute Workload

This panel tracks what the facility is for without assuming that every project is AI training, inference, or cloud capacity.

Undisclosed / unknownUnknown

No source-backed workload, customer, hardware, or training/inference allocation is attached to this record yet.

Workload classification remains unknown in the reviewed record.

Public Money

Business Insider reported proposed tax incentives including a 100% personal-property tax rebate and 80% real-property tax rebate for up to 30 years, with final development terms still contested. A County-hosted May 4 MIDA–Box Elder County agreement sets out three annual $5.4 million upfront payments, with the first due within 30 days of the first building permit, but MIDA's current project page says the interlocal agreement remains a draft and unsigned during the referendum process; no payment record is verified here.

Power

Box Elder County and MIDA materials describe a phased project with 3 GW committed in Phase One and approximately 9 GW at buildout, with developer/county materials describing onsite natural-gas generation. These are planned project and generation contexts, not confirmed data-center IT load or energized capacity.

Bloom / Fuel Cells

No fuel-cell or Bloom Energy source is attached to this project yet.

Core tracking fields have source leads attachedFields with source leads: NDA / secrecy, Public money, Water, Power
Discuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.