A denial is a decision. It is not the end of the paper trail.

A sixth paper trail · Palm Beach County, Florida

A denial is a decision. It is not the end of the paper trail.

Project Tango's expansion request was denied, then challenged. The public record shows a real land-use fight around a proposed data-center footprint; it does not show a built campus, operating workload, or public subsidy.

What the record actually says

Palm Beach County's zoning page identifies PBA Holdings as the applicant for an April 2026 expansion request: 1,032,000 square feet of data-center use inside a 3,594,564-square-foot mixed-use plan on 202.67 acres. That is proposed floor area, not operating capacity or measured demand.

Stet News reported that the requested expansion was denied on July 15, 2026 and challenged on August 5, with a later hearing before a special magistrate. The challenge is a live procedural question; it is not proof that the expansion will proceed. The tracker's other Tango site applications are separate and should not be collapsed into this decision.