Fact sheet
Project Jupiter fact sheet
Project Jupiter, Santa Teresa, Doña Ana County, New Mexico
Status Under construction (confirmed by a source)
- Location
- Santa Teresa, Doña Ana County, New Mexico
- Company, as listed
- Open AI/Oracle
- Size, as listed in the source dataset
- 700 MW reported; Mega campus (>1,000 MW); 3,000,000 sq ft; 1400 acres; expected online 2026
- Power
- Source reviewed September 9, 2026: Oracle says an updated air-quality application replaces the earlier gas-turbine and diesel design with a Bloom fuel-cell microgrid. Bloom separately describes up to 2.45 GW of fuel-cell capacity for the campus. These are planned onsite-generation/project-power figures, not confirmed utility load, energized capacity, or data-center IT load; tariff, interconnection, fuel-supply, and ratepayer records remain separate questions.
- Water
- Source reviewed September 9, 2026: Oracle's updated Project Jupiter power-plan announcement says the fuel-cell microgrid is expected to avoid public drinking water for power generation and data-center cooling and requires only minimal water for power-generation startup fill. The company statement does not publish a facility withdrawal, consumption, cooling, service, or wastewater quantity; those records remain open.
- Money
- Source dataset project_cost field reports $165 billion; public funding records still need local review.
Sources: FracTracker Alliance: Open U.S. Data Centers Tracker; ArcGIS source row: Project Jupiter dataset attributes; El Paso Matters: Dona Ana Billion Dollar Data Center Santa Teresa El Paso Water Meta; El Paso Matters: Project Jupiter Data Center Santa Teresa New Mexico El Paso Texas Water Electricity; KFOX14: Residents Demands Transparency For 165 Billion Santa Teresa Data Center New Mexico NM Dona Ana County Project Jupiter Borderplex Digital; El Paso Matters: Project Jupiter Data Center Santa Teresa Approved Dona Ana Commissioners; Bloomberg: AI Data Center Gets Approval For 165 Billion Phantom Debt Deal; El Paso Matters: Stargate Open AI Oracle Project Jupiter Data Center Dona Ana New Mexico El Paso Texas; Data Center Dynamics: Groups Sue To Stall Data Center Project In Doña Ana County New Mexico; Data Center Dynamics: Oracle Revealed As Tenant Of Project Jupiter Data Center Campus In New Mexico; New Mexico Environmental Law Center: NM Orgs Demand Public Transparency And Access Concerning Project Jupiter Air Quality Permits; Empower New Mexico: Empower New Mexico source; Facebook community group: IndivisibleLASCRUCES; Bloom Energy: Communities Are Right to Ask About the Water Use of AI Infrastructure; Bloom Energy: Bloom Energy and Oracle expand partnership to deploy up to 2.8 GW; Oracle: Public Review Opens for Updated Project Jupiter Power Plan (June 3, 2026)
- Media Monitoring lead with medium location confidence. Use the linked sources to verify status, public money, NDA/secrecy, water, and power details before treating this as a fully documented local record.