Proposed-site record

AWS Gilroy

Media Monitoring lead with high location confidence. Use the linked sources to verify status, public money, NDA/secrecy, water, and power details before treating this as a fully documented local record.

Under constructionconfirmedHigh concern

Site Snapshot

Location
Gilroy, Santa Clara County, California
Operator / sponsor
Amazon
Status / stage
Under construction · under construction
Scale
49-98 MW reported; Large (51-99 MW); 438,500 sq ft; 56 acres; expected online 2026

Data Fields

NDA / secrecyMissing / needs review
Public moneyMissing / needs review
WaterMissing / needs review
PowerMissing / needs review

Public Money

No public funding record attached yet. Local subsidy, tax-abatement, land, bond, and utility records need follow-up.

Water

Source dataset reports cooling source: Hybrid air/water. Water permits and withdrawal records need local sourcing.

Power

Source dataset reports 49-98 MW; power source: Natural gas; 25 2.5MW emergency generators for redundancy purposes generators. Utility tariff, interconnection, and ratepayer records need separate sourcing.

NDA / Secrecy

No NDA reported

Missing NDA / secrecy, Public money, Water, PowerAttached fields: none yet
Draft request for missing recordsSubmit evidenceReport correctionDiscuss this project

Community Discussion

Start a moderated thread for local questions, meeting notes, public-records coordination, or context that should not be treated as verified evidence yet.

Start Project Thread

Sources and Leads

These links are the current public trail for this record. Treat broad dataset links as leads; local documents and reporting carry more weight.